PPRA & GCC • Guide
The Delay Happened — So Why Didn’t the Contractor Get More Time?
It is Monday morning on a construction site.
The contractor is ready to proceed with the next major activity, but an important drawing has still not been issued.
The site team has already raised the issue several times. It has been discussed in meetings. The Project Manager knows about it. Everyone agrees that the work cannot proceed as originally planned.
Two weeks pass.
Then another week.
Eventually, the drawing arrives.
The contractor has now lost valuable time.
But there is a problem.
The contractor never issued the contractual notice required to protect its claim for an Extension of Time.
At the end of the project, the contractor submits an EOT claim and explains that the delayed drawing affected the programme.
The Employer's response is simple:
“Why wasn't this notified when it happened?”
This is where many contractors discover an uncomfortable truth:
Knowing that a delay happened is not the same as protecting your contractual entitlement arising from that delay.
For contractors working under PPRA-based contracts, delay management is therefore not simply about updating the programme after something goes wrong. It is about identifying the event, giving the required notice, demonstrating its effect on completion, and maintaining the evidence needed to support the claim.
1. First, determine whether the delay may give you an entitlement
Not every delay on a construction site gives the contractor an Extension of Time.
A contractor must first ask:
What caused the delay, and does the contract provide an entitlement for that cause?
Under the PPRA General Conditions of Contract for Construction of Medium and Large Works, Sub-Clause 8.4 provides for Extension of Time where completion is or will be delayed by specified causes.
These include, among others:
- Variations or substantial changes in quantities;
- causes of delay that give an entitlement under another provision of the contract;
- exceptionally adverse climatic conditions;
- certain unforeseeable shortages caused by epidemic or government action; and
- delay, impediment or prevention caused by or attributable to the Employer, Employer's Personnel or the Employer's other contractors.
Other provisions can also create specific entitlements.
For example, where the Employer fails to provide access to or possession of the Site within the required time, the contract provides a route to an Extension of Time, subject to the applicable notice and claim provisions.
Similarly, where necessary drawings or instructions are not issued within a reasonable time, the contractor is required to notify the Project Manager and may become entitled to an Extension of Time and, where the contractual conditions are satisfied, related Cost.
The important lesson is this:
Do not wait until the end of the project to decide whether an event was a delay event.
Start assessing it when it happens.
2. A delay discussion is not automatically a contractual notice
This is one of the most important distinctions for a contractor.
You may have:
- discussed the delay during the site meeting;
- mentioned it to the Project Manager;
- recorded it in the site diary;
- sent a WhatsApp message;
- complained verbally on site; or
- included it in a progress meeting presentation.
All of these may help establish what happened.
But they should not automatically be treated as a substitute for the contractual notice required by the contract.
Under the PPRA Medium and Large Works GCC, contractual communications such as notices are to be in writing and delivered using the method specified by the contract/SCC. The GCC also contains specific notice requirements for contractor claims.
That distinction matters because a delay claim is ultimately an evidence exercise.
You need to be able to demonstrate:
This happened → we notified it → it affected the works → it affected completion → we complied with the contractual procedure.
3. The 28-day clock can become critical
This is where delay administration becomes serious.
Under Sub-Clause 20.1 of the PPRA Medium and Large Works GCC, where the contractor considers itself entitled to an Extension of Time and/or additional payment, it must give notice to the Project Manager describing the event or circumstance giving rise to the claim.
The notice is to be given as soon as practicable and not later than 28 days after the contractor became aware, or should have become aware, of the event or circumstance.
The consequence of missing that period is significant: under that particular GCC, the Time for Completion is not extended and the contractor is not entitled to additional payment for the claim, with the Employer discharged from liability in connection with the claim.
This is why a contractor should never think:
“Let's wait and see whether the delay becomes serious.”
By the time the effect becomes obvious, the contractual notice period may already have passed.
4. What should the initial delay notice contain?
A good notice does not need to contain the entire EOT claim.
The purpose of the initial notice is to put the Project Manager on clear notice of the event or circumstance and the contractor's potential entitlement.
At a minimum, the contractor should clearly identify:
1. The contract
State the:
- Contract name;
- Contract number;
- project;
- relevant correspondence reference; and
- date.
2. The event
Explain exactly what happened.
For example:
Drawing S-204 required for the reinforced concrete works at Block B has not yet been issued.
Avoid vague statements such as:
“The project is delayed because drawings are late.”
3. When it happened
State:
- when the issue first arose;
- when the contractor became aware of it;
- what action was expected; and
- how long the issue has remained unresolved.
4. The affected work
Identify the activities that cannot proceed, or that have been disrupted.
For example:
Foundation excavation → blinding → reinforcement → concrete casting
If reinforcement cannot proceed because the structural detail has not been issued, say so.
5. The potential time effect
Give the current assessment of the likely impact.
At this stage, you may not yet know the final number of days.
That is acceptable if the event is still developing.
The contractor can state that the delay is being monitored and that further particulars will be submitted as the effect becomes clearer, subject to the contract's requirements.
5. Do not confuse the notice with the EOT submission
This is another common mistake.
The initial notice and the detailed EOT claim/submission are not necessarily the same document.
Think of them as two stages.
Stage 1 — Protect the entitlement
“This event has occurred and may delay completion. We are notifying you in accordance with the Contract.”
Stage 2 — Demonstrate the entitlement
“Here is the evidence showing how this event actually affected the programme and the completion date.”
The second stage may require considerably more information.
Depending on the contract and circumstances, this can include:
- the approved baseline programme;
- updated programmes;
- affected activities;
- critical path information;
- correspondence;
- instructions;
- drawings and drawing registers;
- site records;
- photographs;
- meeting minutes;
- daily reports;
- resource records;
- progress measurements;
- delay analysis; and
- mitigation measures taken by the contractor.
The principle is simple:
The notice protects the claim. The evidence proves the claim.
6. Your programme must tell the story of the delay
Imagine that your original programme showed:
Structural Drawing → Reinforcement → Inspection → Concrete → Blockwork
Now imagine the structural drawing is delayed by 21 days.
Simply saying:
“Drawing delayed by 21 days, therefore EOT = 21 days”
may not be enough.
What if the contractor had sufficient float?
What if another work front was available?
What if the activity was not actually on the critical path?
What if the contractor was already behind for its own reasons?
What if the delayed drawing affected one activity but did not move the overall Completion Date?
This is why the programme matters.
Under Sub-Clause 8.3 of the PPRA Medium and Large Works GCC, the contractor is required to submit a detailed programme and revise it when the previous programme becomes inconsistent with actual progress or the contractor's obligations. The programme is therefore an important part of managing and demonstrating the effect of delay.
A good delay analysis should answer:
What would have happened if the delaying event had not occurred?
and then:
What happened because the event occurred?
That difference is where the time entitlement is established.
7. Keep updating the programme as the project changes
One of the worst habits a contractor can develop is keeping the original programme unchanged while the actual project moves further and further away from it.
The original programme remains important because it establishes the planned sequence.
But it cannot tell the whole story after months of actual project changes.
The PPRA GCC requires revised programmes where the previous programme is inconsistent with actual progress or the contractor's obligations.
Therefore, a contractor should maintain a disciplined cycle:
Baseline Programme
↓
Actual Progress
↓
Identify Variance
↓
Identify Cause
↓
Issue Required Notice
↓
Update Programme
↓
Assess Impact on Completion
↓
Submit Supporting Particulars
This creates a continuous project record instead of trying to reconstruct the entire history six months later.
8. Keep evidence while the event is happening
Suppose the Project Manager says:
“We are waiting for the revised structural drawings.”
Do not simply write that sentence in your notebook.
Build an evidence trail.
Record:
- date the drawing was requested;
- drawing reference;
- date promised;
- date actually received;
- affected activity;
- work that could not proceed;
- alternative work available;
- labour affected;
- equipment affected;
- photographs;
- related correspondence;
- site meeting discussions;
- programme impact; and
- mitigation actions.
This is much stronger than trying to remember everything when preparing an EOT submission several months later.
9. Keep proving that the delay was not caused by you
This is particularly important.
A contractor cannot simply identify an Employer-related event and assume every day that follows becomes an entitlement.
The analysis must consider the contractor's own responsibility.
For example:
The Employer delays a drawing by 14 days.
But during those same 14 days, the contractor also has an unresolved procurement problem that would have prevented the affected activity from proceeding.
The contractor cannot automatically claim all 14 days as Employer delay.
The analysis has to consider what actually affected completion.
This is why contemporary records matter.
They allow the contractor to distinguish between:
Employer/other qualifying delay
and
Contractor-responsible delay.
10. Mitigation still matters
Protecting your entitlement does not mean simply sitting back and allowing the project to lose time.
A professional contractor should continue looking for reasonable ways to reduce the effect of the delay.
For example:
If one drawing is delayed, can another work front proceed?
Can procurement continue?
Can another building block be advanced?
Can another activity be brought forward?
Can resources be moved temporarily?
Can a revised sequence reduce the eventual effect on completion?
The objective is not to manufacture delay.
The objective is to demonstrate that the contractor acted professionally and took reasonable steps to minimise its consequences.
The PPRA GCC also specifically requires prompt warning of probable future events or circumstances that may adversely affect the work, increase the Contract Price or delay execution.
A practical delay-management system for contractors
A contractor can simplify the entire process into eight steps:
1. IDENTIFY
What happened?
2. CHECK
Does the contract provide an entitlement for this type of event?
3. NOTIFY
Have we issued the required notice within the contractual period?
4. RECORD
What evidence proves what happened?
5. ANALYSE
Which activities were affected, and did the event affect the critical path or Completion Date?
6. MITIGATE
What reasonable steps can we take to reduce the delay?
7. UPDATE
Does the programme now need to be revised?
8. SUBMIT
Provide the supporting particulars and requested Extension of Time in accordance with the contract.
The workflow becomes:
EVENT → CHECK CONTRACT → NOTICE → RECORD → ANALYSE → MITIGATE → UPDATE PROGRAMME → EOT SUBMISSION
That is much safer than:
EVENT → WAIT → PROJECT FINISHES LATE → WRITE EOT LETTER
The contractor's real protection is not the letter
It is tempting to think that the most important part of an EOT claim is writing a strong letter.
It is not.
The letter is only one part of the system.
A strong EOT position is built throughout the project:
Contract knowledge
+
Timely notices
+
Accurate programmes
+
Contemporaneous records
+
Clear delay analysis
+
Evidence of mitigation
=
A defensible time claim
This is also why project management and contract administration cannot be separated.
A project manager who only monitors physical progress may know that the project is late.
A contractor's commercial and contract administration team must also know:
Why is it late?
Who is responsible?
When did the event occur?
When did we notify it?
What activity did it affect?
Did it affect completion?
What evidence supports our position?
Those questions should be answered while the project is happening—not after the dispute has already started.
How Javenzi can help
This is one of the areas where a connected construction management system becomes useful.
A contractor should not have to search through WhatsApp conversations, email threads, meeting minutes, site diaries and spreadsheets months later just to reconstruct why a project was delayed.
The project record should be connected.
A delay event should be capable of being linked to:
- the relevant project;
- programme activity;
- correspondence;
- instructions;
- documents;
- site records;
- photographs;
- affected dates;
- responsible party;
- notices; and
- the eventual EOT submission.
That creates something much more valuable than a list of project documents.
It creates a traceable project history.
That is the type of information a contractor needs when asking one of the most important questions in project administration:
“Why did we finish later than planned—and can we prove why?”
Javenzi is designed around this broader principle: construction information should not remain scattered across separate files and conversations. It should form one connected construction record that helps the contractor understand what is happening, what changed, and what action is required.
Final takeaway
A delay does not become an entitlement simply because everyone on site knows that it happened.
The contractor must manage the contractual process.
Identify the event.
Check the contract.
Give the required notice on time.
Record what happened.
Connect the event to the programme.
Analyse its effect on completion.
Mitigate where reasonably possible.
Then submit the supporting particulars required by the contract.
Under the PPRA Medium and Large Works GCC, Sub-Clause 20.1 makes timely notice particularly important: failure to give the required claim notice within the specified 28-day period can have serious consequences for both Extension of Time and additional payment.
Don't wait until the project is late to start proving why it was delayed.
Protect the entitlement while the event is happening.